Unknown Group Files CEQA Suit against Nishi at the 11th Hour

Friday was the last day to file a CEQA suit against Nishi, and just after 10 am, the city received notice of the commencement of action against it by Sacramento-based law firm, Soluri Meserve, on behalf of purported client Davis Coalition for Sensible Planning.  City officials were unaware of who was behind the effort, and Michael Harrington has denied involvement.

Few details are available, as the official complaint was expected to be formally filed on March 9, but it had not been served on the city at the time of publication.

The petitioner challenges that “the City’s approvals of the Nishi Residential Development project.”  They explain, “The lawsuit will be based on violations of CEQA and other claims, as discussed more fully in the Project’s administrative and environmental review proceedings.”

While there are few details, the group does seem to be the same as the one which sent a letter warning of such a challenge on February 6.

They challenged in the letter the city’s attempt “to rely on a CEQA [California Environmental Quality Act] Addendum for its approval of the project.”

In their letter they argue that “an EIR [Environmental Impact Report] Addendum can only be used where (i) there are no additional significant impacts on the environment, and (ii) there are no substantial increases in the severity of previously identified significant impacts.”

The lawyer argues that “there are potentially both new significant impacts and substantial increases in the severity of existing significant impacts. Accordingly, the City must prepare a supplemental EIR for the Revised Project.”

So they argue instead: “A supplemental EIR is required because there are new related projects that could not have been known at the time the EIR was certified, which, when considered cumulatively,
will substantially increase the project’s significant impacts on agricultural and forest resources.”

They argue: “Further, the EIR Addendum did not include an updated related project list or disclose new information with respect to related projects and their cumulative impacts on agricultural resources. Thus, the Addendum also fails as an informational document.”

On air quality, they argue: “A supplemental EIR is required because the Revised Project will potentially increase the project’s significant air quality impacts by exposing the additional residents to substantial pollutant concentrations.”

They write: “The EIR concluded that residential land uses, as sensitive receptors, would be exposed to toxic air contaminants, diesel PM [particulate matter], and ultrafine particulate matter generated by nearby trains on the Union Pacific Railroad and vehicle activity on the I-80, and that the resulting health impacts were significant. By adding approximately 280 more residents, the Revised Project substantially increases that significant impact, triggering the need to prepare and circulate a supplemental EIR.”

They letter argues that the Addendum incorrectly cites the 2015 case of California Building Industry Association v. Bay Area Air Quality Management District.  They argue that “the rule it established does not apply where the Project would exacerbate existing conditions, and the Revised Project (as well as the previously-analyzed Project) would exacerbate the existing conditions by, for instance, adding more automobiles and trucks (through consumption of goods in Davis) to the existing roadways, including the I-80, and by increasing ridership on passenger trains running on the Union Pacific Railroad.”

They argue: “The Addendum is premised on legal error, and also fails as a legal document, by relying on CBIA [California Building Inspection Association] to suggest that the Revised Project’s health risk is less than significant.”

With regard to greenhouse gas (GHG) emissions, they write, “The California Supreme Court has recently stressed the importance of tracking changed conditions and new information in the area of greenhouse gas emissions.”

Yet, they argue that “the EIR Addendum does not account for the changed regulatory conditions and new information related to GHG Emissions.”

They argue, “Since the state’s goals are now stricter, that analysis would have resulted in findings of more severe significant impacts.”  And they add, “The same is true for reliance on the now outdated 2013 CalGreen Title 24 building standards, the 2012 SACOG MTP/SCS, other applicable plans, which when analyzed would result in more severe significant impacts. Individually these updates require a supplemental EIR, but when taken together, the necessity is compounded.”

Further they argue that the revised project “has substantially changed the land use mix by eliminating the research and development portion of the Project. Accordingly, the land use consistency analysis is no longer accurate and must be updated, especially in terms of consistency with the General Plan.”

With respect to noise: “A supplemental EIR must be prepared and circulated because the revised project will substantially increase the project’s significant noise impacts by exposing additional residents to substantial noise.”

On transportation and circulation, “The Project was originally designed with two points of vehicular access. The Revised Project, however, eliminated the public vehicular access via Olive Drive. Thus, the only public vehicular access is through the UC Davis campus.”

They make the argument that “the Revised Project’s single vehicular access is uncertain. The EIR Addendum fails as an informational document because it does not disclose this uncertainty. Further, a reasonable possibility exists that the Project could require alternate vehicular access, or be denied vehicular access altogether.”

The petitioners concluded that “the requested General Plan Amendment is not supported by the record.”

They continue, “[T]he Revised Project has substantially changed the land use mix by eliminating the research and development portion of the project. Accordingly, the land use consistency analysis is no longer accurate and must be updated. The brief analysis in the staff report is insufficient because it does not meaningfully address the changed conditions, and only provides a cursory analysis of Policy LU O.1.”

They argue that “the City Council cannot place the revised project on the ballot for voter approval under Measure J/R.”

It is worth noting that no legal challenge to land use decisions in recent years has received judicial validation in a court of law.  There have been a number of out-of-court settlements, for instance with the water project, the hotel conference center, and the Marriott.  However, when a judge has issued a ruling, they have found the city in compliance, including the most recent Nishi decision.

Many, however, have come to believe that the lawsuit against Nishi last time out played a role in its electoral defeat, even though the affordable housing challenge completely missed the change in the law under the Palmer decision.

—David M. Greenwald reporting



Enter the maximum amount you want to pay each month
$
USD
Sign up for

Author

  • David Greenwald

    Greenwald is the founder, editor, and executive director of the Davis Vanguard. He founded the Vanguard in 2006. David Greenwald moved to Davis in 1996 to attend Graduate School at UC Davis in Political Science. He lives in South Davis with his wife Cecilia Escamilla Greenwald and three children.

    View all posts

Categories:

Breaking News City of Davis Land Use/Open Space

Tags:

9 comments

  1. Just gotta’ love the tactic… have the suit already to go, the preparation of which probably began a couple of months ago, then filing mid-morning of the last day to do so… kinda like Lucy, Charlie Brown, and the football…

    1. Not a comment regarding the lawsuit or Nishi, but at what point do you blame “Charlie Brown” for being so gullible and persistent, and pursuing a game that “Lucy” might not actually want to play?

    1. They’ll have to demonstrate that in the process, but not for a simple ‘filing’, as I understand it… they will have to no later that the first hearing in front of a judge, I believe… I think it is pro forma that the City will raise the exact same question when it ‘responds’…

      Maybe one of the attorneys out there can give a better, more accurate response to your question…

      1. Another point… at the end of the day, issues have to be apparently “substantial” and not petty, trivial, purely technical, for it to pass the first ‘litmus test’.   Just can’t see from the narrative that the suit will pass the ‘smell test’, and that the election could be delayed… worst case scenario is that the judge withholds certification of that measure’s results, pending decision, but I’m not an attorney….

         

Leave a Comment